SPECIAL REPORT: FG Gives Detailed Expenditure Breakdown Of N162.5b SUKUK Funds

July 26, 2020
185 Views

Senior Special Assistant to Nigerian President Muhammadu Buhari on Public Affairs, Ajuri Ngelale on Sunday published the complete Expenditure Breakdown Of N162.5b SUKUK Funds Released For 44 Road Projects Across The Nation’s Six Geo-Political Zones.

Ngelale said the intention behind delivering this breakdown is to offer insight for public accountability. 

This is coming as TrackaNg, a project by Civic Technology Organization, earlier today promised Nigerians a tracking of the SUKUK Funds projects.

Ngelale listed the projects as follows:

Zonal Breakdown:

North-Central:
N26.5bn (2020)
143.44 kms (2020)
8 Roads

North-East:
N30.5bn
277.53 kms
8 Roads

North-West:
N26.5bn
227.47 kms
7 Roads

South-West:
N27bn
59.74 kms
6 Roads

South-East:
N26bn
99.45 kms
5 Roads

South-South:
N26bn
121.78 kms
10 Roads

NORTH-CENTRAL BREAKDOWN: EIGHT ROADS

(1) Dualization Of Suleja-minna Road PHASE II (KM 40+000 – 101+000) In Niger State.

Contractor: Salini Nigeria Ltd
Contract Sum: N36.2bn
Current Completion Level: 17.20%
2020 SUKUK Payment: N2.5bn
Road/Bridge Works
Kms Covered (2020): 14km

(2) Abuja-abaji Road (Section 1: International
airport Link Road JCT – Sheda Village JCT)

Contractor: Dantata & Sawoe
Contract Sum: N28.6bn
Current Completion Level: 96.11%
2020 SUKUK Payment: N1.0bn
PROJECT COMPLETION
Kms Covered (2020): 2.2km

(3) Abuja-lokoja Road: Section Iv (Koton Karfe – Lokoja)

Contractor: Gitto Construction
Contract Sum: N31.08bn
Current Completion Level: 76.0%
2020 SUKUK Payment: N2.5bn
Asphalt Wearing and 1st & 2nd Coat surface dressing on shoulders with lined drains
Kms Covered (2020): 5.5km

(4) Dualization Of Obajana Junction To Benin
phase 2: Section 1 (Obajana Junction To Okene)

Contractor: CGC Nigeria Ltd
Contract Sum: N30.56bn
Current Completion Level: 32.66%
2020 SUKUK Payment: N3.5bn
Ongoing Dualization works
Kms Covered (2020): 63.05km

(5) Construction Of Oju/loko-oweto Bridge To
link Benue & Nasarawa With New Approach Roads.

Contractor: RCC Nigeria Ltd
Contract Sum: N51.61bn
Current Completion Level: 96.7%
2020 SUKUK Payment: N6.0bn
PROJECT COMPLETION
Kms Covered (2020): 5.0km

(6) Reconstruction Of Bida-lapai-lambata Road In Niger State.

Contractor: CGC Nigeria Ltd
Contract Sum: N33.3bn
Current Completion Level: 13.06%
2020 SUKUK Payment: N5.0bn
CH25+000 – CH35+500, CH43+600 – CH55+000 up to A/C Wearing Course
Kms Covered (2020): 20.9km

(7) Reconstruction Of Makurdi-Naka-Adoka-ankpa Road In Benue State.

Contractor: Gilmor Engineering
Contract Sum: N27bn
Current Completion Level: 0.53%
2020 SUKUK Payment: N3.0bn
CH70+500 – CH58 (12.5Km), CH70+650 – CH150 (12.5Km) up to A/C Binder Course
Kms Covered (2020): 25.0km

(8) Construction Of Road Linking Baro Port To Gulu Town In Niger State

Contractor: GR Building Nigeria
Contract Sum: N10.61bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
PROJECT COMMENCEMENT
Kms Covered (2020): 7.75km

NORTH-EAST BREAKDOWN: EIGHT ROADS

(1) Kanomaiduguri Road: (Section Ii – Shuari Link To Azare)

Contractor: Setraco Nigeria Ltd
Contract Sum: N65.31bn
Current Completion Level: 86.62%
2020 SUKUK Payment: N11.0bn
Ongoing Construction
Kms Covered (2020): 53.93km

(2) Kano-maiduguri Road: (Section Iii – Azare Link To Potiskum)

Contractor: Mothercat Ltd
Contract Sum: N45.18bn
Current Completion Level: 91.79%
2020 SUKUK Payment: N2.0bn
PROJECT COMPLETION
Kms Covered (2020): 0km – Toll Plazas/Weighbridges

(3) Kano-maiduguri Road: (Section Iv – Potiskum Link To Damaturu)

Contractor: CGC Nigeria Ltd
Contract Sum: N51.90bn
Current Completion Level: 80.51%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 94.0km

(4) Kano-maiduguri Road: (Section V – Damaturu Link To Maiduguri)

Contractor: CCECC Nigeria Ltd
Contract Sum: N67.79bn
Current Completion Level: 50.94%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 59.6km

(5) Rehabilitation Of Gwoza-damboa-Goniri-ngamdu In Borno State

Contractor: Hajaig Construction Nigeria Ltd
Contract Sum: N34.60bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
Site Clearing/Earthworks, Culverts, Pavement & Surfacing
Kms Covered (2020): 15.0km

(6) Reconstruction Of Mayo Belwa-jada-Ganye-Tougo Road In Adamawa State

Contractor: Triacta Nigeria Ltd
Contract Sum: N22.69bn
Current Completion Level: 14.14%
2020 SUKUK Payment: N3.0bn
Asphalt Wearing & Reconstruction
Kms Covered (2020): 42.0km

(7) Construction Of Ibi Bridge In Taraba State

Contractor: RCC Nigeria Ltd
Contract Sum: N57.07bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.0bn
Piles and Pile caps for Axis 2 & 3, 4 & 5 Ibi Side
Kms Covered (2020): Bridgeworks

(8) Rehabilitation Of Nguru-gashua-Bayamari
road: Section II (Gashua-bayamari) In Yobe State

Contractor: Ric Roc Construction Ltd
Contract Sum: N11.77bn
Current Completion Level: 0.14%
2020 SUKUK Payment: N1.5bn
Rehabilitation up to Asphalt Binder
Kms Covered (2020): 13.0km

NORTH-WEST BREAKDOWN: SEVEN ROADS

(1) Kano-maiduguri Road: (Section I – Kano Link To Wudil With Link To Shuari)

Contractor: Dantata & Sawoe
Contract Sum: N55.1bn
Current Completion Level: 67.51%
2020 SUKUK Payment: N4.5bn
Interchange 1,2 & Carriageway
Kms Covered (2020): 58.0km

(2) Dualization Of Kano-katsina Road: (Phase 1 – Kano Town At Dawanau RoundAbout To
Katsina State Border) In Kano State

Contractor: CCECC Nigeria Ltd
Contract Sum: N14.0bn
Current Completion Level: 51.48%
2020 SUKUK Payment: N2.75bn
Ongoing Dualization
Kms Covered (2020): 57.0km

(3) Construction Of Kaduna Eastern By-pass

Contractor: Eksiogulari Nigeria Ltd
Contract Sum: N38.19bn
Current Completion Level: 39.40%
2020 SUKUK Payment: N4.0bn
CH16+000 – CH37+000 (Road Works up to A/C Binder Course), Bridgeworks at Chikaji CH35
Kms Covered (2020): 21.0km

(4) Construction Of Kano Western By-pass

Contractor: Dantata & Sawoe
Contract Sum: N22.77bn
Current Completion Level: 66.98%
2020 SUKUK Payment: N4.0bn
Asphalt Wearing; Bridgework (3 & 4); CH 0+425 – CH 9+030 Median Drain & Slope Protection (Bridge 2)
Kms Covered (2020): 12.47km

(5) Dualization Of Kano-katsina Road: (Phase II – Kano/katsina Border Link To Katsina
Steeling Mills Roundabout)

Contractor: CCECC Nigeria Ltd
Contract Sum: N29.65bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.75bn
Ongoing DualizatiSTEELon
Kms Covered (2020): 26.5km

(6) Rehabilitation Of Sokoto-tambuwal-Jega-kontagora-makera Road: (Section I – Sokoto / Kebbi States)

Contractor: Triacta Nigeria Ltd
Contract Sum: N30.45bn
Current Completion Level: 68.52%
2020 SUKUK Payment: N5.0bn
Carriageway Reconstruction
Kms Covered (2020): 40.0km

(7) Rehabilitation Of Ajingi-jahun-kafin Hausa
Road In Jigawa State

Contractor: H & M Nigeria Ltd
Contract Sum: N25.03bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.5bn
Carriageway Reconstruction
Kms Covered (2020): 12.5km

SOUTH-EAST BREAKDOWN: FIVE ROADS

(1) ENUGU-PH DUAL CARRIAGEWAY: (LOKPANTA-UMUAHIA)

Contractor: Setraco Nigeria
Contract Sum: N39.54bn
Current Completion Level: 64%
2020 SUKUK Payment: N5.0bn
Kms Covered (2020): 21.7km

(2) RECONSTRUCTION OF ENUGU-PORT HARCOURT DUAL CARRIAGEWAY: (SECTION II – UMUAHIA TO ABA)

Contractor: Arab Contractors Ltd
Contract Sum: N50.89bn
Current Completion Level: 36.21%
2020 SUKUK Payment: N5.5bn
Carriageway Construction
Kms Covered (2020): 25.75km

(3) RECONSTRUCTION OF ENUGU-PORT HARCOURT ROAD: (SECTION III – ENUGU TO LOKPANTA)

Contractor: CGC Nigeria Ltd
Contract Sum: N32.31bn
Current Completion Level: 28.77%
2020 SUKUK Payment: N5.0bn
Carriageway Construction
Kms Covered (2020): 27.0km

(4) RECONSTRUCTION OF ONITSHA-ENUGU EXPRESSWAY: (SECTION I – AMANSEA TO ENUGU
STATE BORDER)

Contractor: RCC Nigeria Ltd
Contract Sum: N62.06bn
Current Completion Level: 29.92%
2020 SUKUK Payment: N6.5bn
Carriageway Reconstruction
Kms Covered (2020): 12.0km

(5) RECONSTRUCTION OF OLD ENUGU-ONITSHA ROAD: (OPI JUNCTION-UKEHE OKPATU-ABOH UDI-OJI TO
ANAMBRA BORDER)

Contractor: Arab Contractors
Contract Sum: N31.94bn
Current Completion Level: 4.75%
2020 SUKUK Payment: N4.0bn
Carriageway Reconstruction
Kms Covered (2020): 13.0km

SOUTH-WEST BREAKDOWN: SIX ROADS

(1) RECONSTRUCTION OF BENIN-OFOSU-ORE-AJEBANDELE-SHAGAMU EXPRESSWAY

Contractor: RCC Nigeria Ltd
Contract Sum: N65.22bn
Current Completion Level: 82.96%
2020 SUKUK Payment: N4.5bn
Carriageway Reconstruction
Kms Covered (2020): 15.0km

(2) PAVEMENT STRENGTHENING AND ASPHALT OVERLAY
OF AJEBANDELE-IJEBU ODE-SHAGAMU ROAD IN
OGUN STATE

Contractor: RCC Nigeria Ltd
Contract Sum: N71.64bn
Current Completion Level: 26.50%
2020 SUKUK Payment: N4.5bn
Asphalt Overlay & Pavement Reinforcement
Kms Covered (2020): 13.0km

(3) DUALIZATION OF IBADANILORIN EXPRESSWAY: (SECTION II – OYO-OGBOMOSO ROAD IN OYO STATE)

Contractor: RCC Nigeria Ltd
Contract Sum: N47.50bn
Current Completion Level: 73.35%
2020 SUKUK Payment: N5.0bn
Ongoing Dualization; Piling; Pile Caps
Kms Covered (2020): 8.0km

(4) REHABILITATION AND EXPANSION OF LAGOS-BADAGRY EXPRESSWAY: (SECTION I – AGBARA JUNCTION TO BENIN BORDER)

Contractor: CGC Nigeria Ltd
Contract Sum: N63.02bn
Current Completion Level: 9.30%
2020 SUKUK Payment: N4.5bn
Ongoing Expansion works
Kms Covered (2020): 8.70km

(5) REHABILITATION OF THE OUTER MARINA ROAD IN
LAGOS STATE

Contractor: CCECC Nigeria Ltd
Contract Sum: N9.27bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N4.0bn
Reconstruction works
Kms Covered (2020): 4.54km

(6)  DUALIZATION OF LAGOS-OTTA ROAD

Contractor: Julius Berger
Contract Sum: N56.70bn
Current Completion Level: 15.38%
2020 SUKUK Payment: N4.557bn
Carriageway Reconstruction
Kms Covered (2020): 10.50km

SOUTH-SOUTH BREAKDOWN: TEN ROADS

(1) DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION II – OKENE TO AUCHI)

Contractor: Mothercat Ltd
Contract Sum: N21.29bn
Current Completion Level: 48.85%
2020 SUKUK Payment: N4.0bn
Carriageway & Bridgeworks
Kms Covered (2020): 56.87km

(2) DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION III – AUCHI TO EHOR)

Contractor: Dantata & Sawoe
Contract Sum: N34.86bn
Current Completion Level: 13.41%
2020 SUKUK Payment: N4.0bn
Dualization, Bridgeworks & Drainage works
Kms Covered (2020): 23.0km

(3) DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION IV – EHOR TO BENIN)

Contractor: RCC Nigeria Ltd
Contract Sum: N35.25bn
Current Completion Level: 39.68%
2020 SUKUK Payment: N3.5bn
Dualization & Drainage works
Kms Covered (2020): 9.0km

(4) RECONSTRUCTION OF ENUGU-PORT HARCOURT ROAD: (SECTION IV – ABA-PORT HARCOURT EXPWY)

Contractor: CCECC Nigeria Ltd
Contract Sum: N40.35bn
Current Completion Level: 23.74%
2020 SUKUK Payment: N3.0bn
Expansion from four to eight lanes
Kms Covered (2020): 3.48km

(5) DUALIZATION OF YENEGWE-KOLO-OTUOKE-BAYELSA PALM ROAD

Contractor: CCECC Nigeria Ltd
Contract Sum: N26.49bn
Current Completion Level: 20.50%
2020 SUKUK Payment: N2.0bn
Ongoing Dualization
Kms Covered (2020): 3.50km

(6) CONSTRUCTION OF IKOM BRIDGE IN CROSS RIVER
STATE

Contractor: Setraco Nigeria Ltd
Contract Sum: N8.91bn
Current Completion Level: 45.02%
2020 SUKUK Payment: N2.0bn
Bridgeworks
Kms Covered (2020): 1.20km

(7) RECONSTRUCTION OF ODUKPANI-ITU-IKOT EKPENE
ROAD IN CROSS RIVER STATE: (SECTION I – ODUKPANI-ITU BRIDGE)

Contractor: Julius Berger
Contract Sum: N54.17bn
Current Completion Level: 1.82%
2020 SUKUK Payment: N3.0bn
Dual Carriageway works
Kms Covered (2020): 4.0km

(8) DUALIZATION OF SAPELE-EWU ROAD: (SECTION I – SAPELE-AGBOR IN DELTA STATE)

Contractor: CGC Nigeria Ltd
Contract Sum: N64.87bn
Current Completion Level: 8.80%
2020 SUKUK Payment: N1.5bn
Dual Carriageway works
Kms Covered (2020): 3.0km

(9) DUALIZATION OF SAPELE-EWU ROAD: (SECTION II – AGBOR-EWU IN DELTA STATE)

Contractor: Setraco Nigeria Ltd
Contract Sum: N47.94bn
Current Completion Level: 13.98%
2020 SUKUK Payment: N1.5bn
Dual Carriageway works
Kms Covered (2020): 7.73km

(9) DUALIZATION OF SAPELE-EWU ROAD: (SECTION II – AGBOR-EWU IN DELTA STATE)

Contractor: Setraco Nigeria Ltd
Contract Sum: N47.94bn
Current Completion Level: 13.98%
2020 SUKUK Payment: N1.5bn
Dual Carriageway works
Kms Covered (2020): 7.73km

(10) RECONSTRUCTION OF ALESI-UGEP ROAD: (IYAMOYUNG-UGEP) SECTION IN CROSS RIVER STATE

Contractor: Sermatech Nigeria Ltd
Contract Sum: N11.22bn
Current Completion Level: 91.0%
2020 SUKUK Payment: N1.5bn
Carriageway works
Kms Covered (2020): 10.0km

“This Concludes The Breakdown Of The 44 SUKUK Funded Roads Earmarked For Construction With N162.5bn In Cash Released For 2020. With This, CSOs And Other Interest Groups Are Best Placed To Hold Contractors Across The Nation Accountable For Funds Paid To Them. God Bless Nigeria”– Ajuri Ngelale, Senior Special Assistant to President Muhammadu Buhari on Public Affairs.

You may be interested

2024 CHANQ: History Not Kind To Us Against Ghana –Ogunmodede
Sports
1 views
Sports
1 views

2024 CHANQ: History Not Kind To Us Against Ghana –Ogunmodede

Webby - December 24, 2024

Home-based Super Eagles coach Daniel Ogunmodede says history has not been good to Nigeria when they face rivals Ghana.The home-based…

Ex-Chelsea Star Oscar Returns To Boyhood Club Sao Paulo
Sports
2 views
Sports
2 views

Ex-Chelsea Star Oscar Returns To Boyhood Club Sao Paulo

Webby - December 24, 2024

Former Chelsea midfielder Oscar is returning to his Brazilian boyhood club Sao Paulo after 14 years, which included a long…

‘I’m Incredibly Proud’– Arokodare Talks Up Genk’s Unbeaten Home Streak
Sports
1 views
Sports
1 views

‘I’m Incredibly Proud’– Arokodare Talks Up Genk’s Unbeaten Home Streak

Webby - December 23, 2024

Tolu Arokodare is full of excitement followingGenk’s historic victory over Anderlecht, reports Completesports.com.Sunday’s win at the Cegeka Arena was the…

Leave a Comment

Your email address will not be published.