While there have been mixed feelings in the sector over the actualization of this dream and if this refinery won’t be delay due to the Nigerian factor, the Executive Director Devakumar Edwin, who oversees the project, described the suggestion that the refinery is unlikely to start production until 2022 as the product of “someone’s wild imagination”.
“Ninety-five percent of engineering has been completed, 90 percent of procurement has been completed. We started civil works in July last year and we have scheduled 2-1/2 years for mechanical completion,” he said, referring to when the plant is ready to be handed over for commissioning.
Aliko Dangote had said he hoped to finish building the refinery, which cost around $14 billion in 2019 and to start production in early 2020. The component is one of the biggest in the world.
Invest & Get 20% In Just 90 Days
Click HERE >>
Delicious Noodles Pizza In Lagos
Click HERE >>
To Buy Cheap MTN & GLO Data
Click HERE >>
You may be interested
Arsenal Equal Chelsea’s London Derby Feat After 5-1 Win Vs Palace
Webby - December 21, 2024Arsenal equaled Chelsea’s London derby achievement following their 5-1 win against Crystal Palace in Saturday’s Premier League game at Selhurst…
Haaland Backs Guardiola To Turn Man City’s Poor Form Around
Webby - December 21, 2024Erling Haaland had said he and his Manchester City teammates are still backing manager Pep Guardiola to turn the team’s…
PSG To Reignite Interest In Osimhen
Webby - December 21, 2024Paris Saint-Germain have contacted Napoli to discuss signing Victor Osimhen in January, according to reports in France.It is reported that…